TitleColorado-Yuma-Smothers
Site Development StatusAvailable
Lease or SaleLease Only
Site Available (Acres)748.0
Lease Rate, Year 1$375Annual Escalator2%
Sales Price Per Acre or Site 
SummaryProperty Parcels

PARCEL
Acreage
R224039
40
R425039
153.6
R426110
80
R426027
80
R426021
160
R426002
160
R426024
80
Total Acreage
753.6


Property Characteristics
[ 753.6 ] Number of acres available for lease or sale?

James
[ yes ] Is the property immediately contiguous to a substation?

[ NK ] What is the maximum transmission capacity of the line (ampacity)?

[ 69KV ] What is the maximum voltage of the line?

[ NO ] Does the property require extensive grading?

[ LOW ] Low, Medium or High Local Utility Rates & Costs

[ $2,500 ] What is the comparable price for this kind of land in the area?

Local Loads:
130 MW Summer
30 MW Winter

Highline, Morgan County REA, KC Electric Association.

System engineer indicates that the 69KV capacity is limited due to low loads in the winter.
Latitude 
Longitude 
Infrastructure Mapping Information, Open Doorshttps://www.arcgis.com/home/webmap/viewer.html?webmap=f928f314504444d8a2d459fc40d2cc07&find=39.71583559,-102.4628153
Site Image
KMZ FileColorado-Yuma-Smothers.kmz
Term Sheethttps://docs.google.com/document/d/e/2PACX-1vTOputlRIbFNE9wNL2tVW5P3pJUQoBJYHckfFvrM8AM6OH2TKoGPHGsRPQtgLOFitysqukbA_tYzagA/pub
CountyYuma
StateColorado
Legal OwnerKirk Smothers
DO NOT CONTACT
For Information
Lane Sharman +1-858-342-1415 lane.sharman@opendoors.com
Energy Community? 
AssignmentLane Sharman
Listing URLhttps://www.ragic.com/ozquantum/real-estate/6/8?embed&hidetop&embedEntry&rmlc=dyidWsv5a8OGr20221212183906ozquantum%2Freal-estate%2F6
Local UtilityY-W Electric Association
Interconnection BriefNone provided.
Owner & Site BriefOwner is motivated to secure an energy development lease.

Development BriefYuma County is an up and coming resource for wind and solar development.

This property is ideally suited for either wind or solar.

Tri-State is motivated to move off of its coal resources.

The line voltage is 69KV, not 115KV as documented in the mapping resource.
Site Analyticsco_80m.jpg
Listing Sequence Number8
Site Characteristics
TypeNotesMap URLImageFileCharacteristic SeqNbr
Substation ID8/12 Interview with Tony McAfferty, Y-W Engineer
Tony confirmed that the substation was a 69KV substation, not 115KV.
Tony will deliver the line ampacity.
He confirms that the lines are owned by Y-W, not Tri-State.
Trent Loutensock was also interviewed and he asserted Tri-State was the line owner before referring me to Tony.
https://www.arcgis.com/home/webmap/viewer.html?webmap=f928f314504444d8a2d459fc40d2cc07&find=39.71583559,-102.4628153  00514